Before work
Starting point
The single-storey house sat between occupied neighbours with limited room for equipment and trucks. A controlled sequence was needed to keep debris inside the footprint and maintain access along the street throughout loading.
On site
Work completed
After required surveys, utility disconnections and permits were confirmed, the structure was reduced inward with machine demolition and water dust suppression. Materials were sorted as the footprint opened, followed by foundation removal and load-out.
Clean handoff
Result
The lot was cleared of the building and below-grade concrete, then backfilled and brought to a stable rough grade. Neighbouring properties remained protected and the builder received an open site ready for survey and excavation planning.